目录简介 | Operation procedures for lifting and laying down of self-electing mast ——————————————————————————————————— 1. Scope This standard specifies the technical requirements, special regulations on the inspection, lifting and laying down of self-erection mast of land rig. This standard is applicable to the lifting and laying down operations of self-erection masts, which lifted and laid down via A-frames of substructure of ZJ - 10, ZJ - 20, ZJ -30, ZJ -40, ZJ - 50 and ZJ - 7U rigs. 2. Normative references The following normative documents contain provisions which, through reference in this standard, constitute provisions of this standard. For dated references, subsequent amendments to, or revisions of, any of these publications (exclude errata) do not apply. However, parties to agreements based on this standard are encouraged to investigate the possibility of applying the most recent editions of the normative documents indicated below. For undated references, the latest edition of the normative document referred to applies. SY/T 5170 Specification for Wire Line for Petroleum and Natural Gas. 3. Inspection and requirements before lifting and laying down 3.1 Mast and substructure 3.1.1 Assemble mast and substructure according to installation instructions and drawings of the rig. 3.1.2 All connecting and fixing parts for mast and substructure shall be complete and proper as required. 3.1.3 The auxiliary facilities such as ladders, hand rails and walkways shall be properly installed and secured. Check and remove any unfixed objects from the mast. 3.1.4 Check the mast and substructure to ensure that there are no cracks, severe distortion, etc.
|