Preview |
1.0.1This Code is formulated with a view to go through with national technical and economic policy in the electrical measuring and energy metering device design process, so as to achieve the accuracy and reliability, state-of-art technology and economic feasibility. 1.0.2This Code is applicable to the design of steam turbine generator and gas turbine plant with new-build or extended unit capacity of 25MW or above, hydraulic power plant (including pumped-storage power generation plant) with unit capacity of 200kW or above, conventionally insular part of nuclear power station, substation (distribution station) with AC nominal voltage of 10kV or above, DC converter station electrical measuring and energy metering devices with DC nominal voltage of 100kV or above. 1.0.3The design of electrical measuring and energy metering device shall not only comply with those specified in this Code, but shall also comply with relevant national current standards and codes. |